|Table of Contents|

[1] Liu Biyu, Chen Weida,. Single-machine scheduling with preventive periodic maintenanceand resumable jobs in remanufacturing system [J]. Journal of Southeast University (English Edition), 2012, 28 (3): 349-353. [doi:10.3969/j.issn.1003-7985.2012.03.017]
Copy

Single-machine scheduling with preventive periodic maintenanceand resumable jobs in remanufacturing system()
Share:

Journal of Southeast University (English Edition)[ISSN:1003-7985/CN:32-1325/N]

Volumn:
28
Issue:
2012 3
Page:
349-353
Research Field:
Economy and Management
Publishing date:
2012-09-30

Info

Title:
Single-machine scheduling with preventive periodic maintenanceand resumable jobs in remanufacturing system
Author(s):
Liu Biyu1 2 Chen Weida1
1School of Economics and Management, Southeast University, Nanjing 211189, China
2School of Management Science and Engineering, Anhui University of Technology, Maanshan 243000, China
Keywords:
single-machine scheduling preventive periodic maintenance resumable jobs LPT-LS algorithm
PACS:
F273
DOI:
10.3969/j.issn.1003-7985.2012.03.017
Abstract:
A single-machine scheduling with preventive periodic maintenance activities in a remanufacturing system including resumable and non-resumable jobs is studied. The objective is to find a schedule to minimize the makespan and an LPT-LS algorithm is proposed. Non-resumable jobs are first scheduled in a machine by the longest processing time(LPT)rule, and then resumable jobs are scheduled by the list scheduling(LS)rule. And the worst-case ratios of this algorithm in three different cases in terms of the value of the total processing time of the resumable jobs(denoted as S2)are discussed. When S2 is longer than the spare time of the machine after the non-resumable jobs are assigned by the LPT rule, it is equal to 1. When S2 falls in between the spare time of the machine by the LPT rule and the optimal schedule rule, it is less than 2. When S2 is less than the spare time of the machine by the optimal schedule rule, it is less than 2. Finally, numerical examples are presented for verification.

References:

[1] Tang O, Grubbstr O M R W, Zanoni S. Planned lead time determination in a make-to-order remanufacturing system [J]. International Journal of Production Economics, 2007, 108(1/2): 426-435.
[2] Arts R H P M, Knapp G M, Mann Jr L. Some aspects of measuring maintenance in the process industry [J]. Journal of Quality in Maintenance Engineering, 1998, 4(1):6-11.
[3] Liao C J, Chen W J. Single-machine scheduling with periodic maintenance and nonresumable jobs [J]. Computers and Operations Research, 2003, 30(9):1335-1347.
[4] Lee C Y. Machine scheduling with an availability constraint [J]. Journal of Global Optimization, 1996, 9(3/4):395-416.
[5] Lee C Y, Liman S D. Single machine flow-time scheduling with scheduled maintenance [J]. Acta Informatica, 1992, 29(4):375-382.
[6] Graves G H, Lee C Y. Scheduling maintenance and semiresumable jobs on a single machine [J]. Naval Research Logistics, 1999, 46(7):845-863.
[7] Ma Y, Yang S L, Chu C B. Minimizing makespan in semiresumable case of single-machine scheduling with an availability constraint [J]. Systems Engineering—Theory & Practice, 2009, 29(4): 128-134.
[8] Chen W J. Minimizing number of tardy jobs on a single machine subject to periodic maintenance [J]. Omega, 2009, 37(3):591-599.
[9] Wu C C, Lee W C. A note on single-machine scheduling with learning effect and an availability constraint [J]. The International Journal of Advanced Manufacturing Technology, 2007, 33(5/6): 540-544.
[10] Yang S J, Yang D L. Minimizing the makespan on single-machine scheduling with aging effect and variable maintenance activities [J]. Omega, 2010, 38(6): 528-533.
[11] Ji M, He Y, Cheng T C E. Single-machine scheduling with periodic maintenance to minimize makespan [J]. Computers & Operations Research, 2007, 34(6): 1764-1770.
[12] Graham R L, Lawler E L, Lenstra J K, et al. Optimization and approximation in deterministic sequencing and scheduling: a survey [J]. Annals of Discrete Mathematics, 1979, 5:287-326.

Memo

Memo:
Biographies: Liu Biyu(1981—), female, graduate, lecturer; Chen Weida(corresponding author), male, doctor, professor, cwd@seu.edu.cn.
Foundation items: The National Natural Science Foundation of China(No.70971022, 71271054), the Scientific Research Innovation Project for College Graduates in Jiangsu Province(No.CXLX-0157), the Scientific Research Foundation of the Education Department of Anhui Province(No.2011sk123).
Citation: Liu Biyu, Chen Weida. Single-machine scheduling with preventive periodic maintenance and resumable jobs in remanufacturing system[J].Journal of Southeast University(English Edition), 2012, 28(3):349-353.[doi:10.3969/j.issn.1003-7985.2012.03.017]
Last Update: 2012-09-20